The idea, step by step
Organise the model before solving
Define variables and units, identify each resource bound and state whether decisions are continuous or whole numbers. A per-unit resource table helps prevent mixing coefficients from different resources. Form the objective separately and include non-negativity, minimum quantities and capacity limits supported by the context.
Explain the recommendation
Find feasible vertices and evaluate the objective at each. State the decision and objective value in context, then check original resource use. Identify unused resources when relevant. An unbounded region can still have a minimum: what matters is whether the objective can improve without limit in a feasible direction.
A common trap
An unbounded region never has an optimum.
Instead: It may have a finite minimum or maximum; examine how the objective changes in permitted directions.
See the thinking
A complete production model
Maximise subject to , and .
- Feasible vertices are .
- Profit values are 0,35,38,30.
- At both resource bounds are used exactly: 10 and 14.
A minimum-cost mix
Minimise subject to , and .
- The lower-bound vertices are .
- Costs are 36,28,32.
- On the horizontal ray to the right of (12,0), cost increases; on the vertical ray above (0,8), cost increases. The connecting boundary segments are linear, so compare their endpoints.
Check your understanding
Maximise for , .
Show answer
Maximum 15 at .
Vertex values are 0,10,15.
Your turn
6 questions · 12 marks · Work at your own pace.
Read the questions online
- Maximise for , , .2 marks
- Maximise for , , .2 marks
- Minimise for , .2 marks
- Why has no finite maximum when only is required?2 marks
- A high-profit proposal uses 18 hours when at most 16 are available. Is it acceptable?2 marks
- The optimum for is . If P is in hundreds of dollars, interpret the result.2 marks
Read the worked solutions
Equivalent correct methods earn the corresponding marks. Include units where asked.
- Maximise for , , .2 marks
The vertices are .
Their values are 0,20,29,24.
Maximum 29 at . - Maximise for , , .2 marks
Vertices are .
Values are 0,27,37,35.
Maximum 37 at . - Minimise for , .2 marks
Rewrite the objective as .
Since and , ; (6,0) attains that bound.
Minimum 12 at . - Why has no finite maximum when only is required?2 marks
Feasible points have arbitrarily large objective t.
It is unbounded above. - A high-profit proposal uses 18 hours when at most 16 are available. Is it acceptable?2 marks
An infeasible decision is excluded regardless of its profit.
No. - The optimum for is . If P is in hundreds of dollars, interpret the result.2 marks
hundreds, so multiply by 100.
AUD 3,800.
Curriculum reference & lesson scope
SACE Board of South Australia
Stage 2 General Mathematics: Modelling with Linear Relationships, a compulsory school-assessed topic. The external examination scope differs from the full course.
Official curriculum source ↗