Connect the ideas
An activity's immediate predecessors must finish before it can start. An arrow shows the permitted direction; its duration is not its drawn length.
In an activity-on-arrow project network, numbered vertices are events. A dashed dummy arrow has zero duration and records a dependency.
A forward scan takes the largest incoming finish time. A backward scan takes the smallest permitted outgoing start time.
The critical path is a longest-duration start-to-finish path. There can be more than one, and shortening one activity need not shorten the project by the same amount.
Total float of an activity is latest head-event time minus earliest tail-event time minus its duration. All times use one stated unit.
An assignment selects exactly one entry in each relevant row and column. Row-by-row cheapest choices can conflict.
Row and column reductions preserve the optimal complete assignment. Independent zeros occupy different rows and columns.
To maximise profit, transform profits into opportunity losses; for a rectangular model, state the meaning and cost of any dummy assignment.
Report the chosen people, tasks, completion time or total cost, together with the assumptions under which the recommendation works.
Practice tests
Complete each paper and show your working.
Networks, scheduling and assignment — Test 1
10 questions · 58 marks · 65 minutes · Scientific calculator
Networks, scheduling and assignment — Test 2
10 questions · 59 marks · 65 minutes · Scientific calculator
Networks, scheduling and assignment — Test 3
10 questions · 58 marks · 75 minutes · Scientific calculator
Networks, scheduling and assignment — Test 4
10 questions · 54 marks · 75 minutes · Scientific calculator
Networks, scheduling and assignment — Test 5
10 questions · 55 marks · 75 minutes · Scientific calculator
Networks, scheduling and assignment — Test 6
10 questions · 60 marks · 75 minutes · Scientific calculator