Year 12 · Networks, scheduling and assignment · 18 min

Dummy activities

Use zero-duration dummy arrows to show dependencies correctly in an activity-on-arrow network.

01 / LEARN

The idea, step by step

A dependency without work

A dummy arrow is a logical link with duration zero. It may be drawn dashed to distinguish it from real work. It consumes no scheduled time and is not an extra task, worker or material cost. It exists because an activity-on-arrow drawing sometimes needs an additional connection to record the correct start rules.

For example, E may need both B and D while C needs A only. Joining all earlier activities at a single event can accidentally force C to wait for B. A carefully placed dummy carries B's dependency to E without changing C's start rule.

Check both sides of the rule

When deciding whether to use a dummy, ask which activities should depend on the incoming task and which should remain independent. After adding it, trace every activity's predecessors again. A dummy that points the wrong way can introduce an impossible cycle or reverse a requirement.

A dummy can affect a forward scan even though its duration is zero: the event at its head must still wait for the tail event to occur. Its own duration does not add time, but the dependency it records may control the start of later work.

A common trap

Deleting a dummy because it has duration zero.

Instead: Zero duration means no extra work, not no dependency. Removing it may let a later activity start before a required predecessor is complete.

02 / WORKED EXAMPLES

See the thinking

Example 1

A zero duration can still matter

A finishes at day 4. B finishes at day 7. A dummy from the end of B enters the event where C starts after A. C lasts 3 days. Find C's earliest finish.

  1. The start event for C waits for both A and the dummy carrying completion of B.
  2. The event occurs at max(4,7)=7.
  3. C then needs 3 days.
C finishes earliest at day 10.
Example 2

Keep one branch independent

A and B start together. C follows A only; D follows both A and B. Explain why making C and D leave one merged A/B finish event is incorrect.

  1. A merged event is reached only after A and B both finish.
  2. C would then be forced to wait for B, which is not required.
  3. Keep C at A's finish and use a dummy connection to make D depend on both.
The merged event adds an unwanted B→C dependency. A dummy can record B→D without adding B→C.

Check your understanding

In the displayed network, what would be lost if the dummy 3→4 were removed?

Show answer

E would no longer be required to wait for B.

E starts at event 4. The dummy is the only connection carrying B's completion from event 3 to event 4.

03 / WORKSHEET

Your turn

6 questions · 13 marks · Work at your own pace.

Read the questions online
  1. For the displayed network, state the duration and purpose of the dashed arrow.
    2 marks
  2. A dummy joins an event reached at time 9 to an event otherwise ready at time 6. What is the earliest time of the receiving event?
    2 marks
  3. P and Q start together. R follows P only, S follows Q only, and T follows both P and Q. Explain why one joint event for the ends of P and Q can be unsuitable.
    3 marks
  4. A student gives a dummy a duration of 2 hours to represent administrative waiting. Is that still a dummy?
    2 marks
  5. Can a dummy have a direct financial cost in this scheduling model? Explain.
    2 marks
  6. A finishes at 5, B at 8, and C at 6. Task D requires all three and takes 4 days. Dummies are used to join the requirements. Find D's earliest finish.
    2 marks
Read the worked solutions

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. For the displayed network, state the duration and purpose of the dashed arrow.
    2 marks

    The arrow 3→4 is a logical connection.

    It records B's completion without adding a real task.

    Duration 0 days; it makes E wait for B as well as D.
  2. A dummy joins an event reached at time 9 to an event otherwise ready at time 6. What is the earliest time of the receiving event?
    2 marks

    The zero-duration dummy arrives at 9+0=9.

    Take max(6,9)=9.

    9.
  3. P and Q start together. R follows P only, S follows Q only, and T follows both P and Q. Explain why one joint event for the ends of P and Q can be unsuitable.
    3 marks

    R and S have different predecessor sets.

    Use separate finish events and logical dummy links to create T's joint requirement.

    It would force R to wait for Q and S to wait for P.
  4. A student gives a dummy a duration of 2 hours to represent administrative waiting. Is that still a dummy?
    2 marks

    A dummy has exactly zero duration.

    A genuine two-hour wait must be modelled as a real timed activity or lag.

    No.
  5. Can a dummy have a direct financial cost in this scheduling model? Explain.
    2 marks

    It represents a dependency only, not real work.

    Costs caused by the resulting schedule must be modelled separately.

    No direct task cost is assigned to a dummy.
  6. A finishes at 5, B at 8, and C at 6. Task D requires all three and takes 4 days. Dummies are used to join the requirements. Find D's earliest finish.
    2 marks

    Its starting event is max(5,8,6)=8.

    Finish time is 8+4=12.

    12 days.
Checking saved progress…

Continue learning

Forward and backward scans

Next lesson
Curriculum reference & lesson scope

SACE Board of South Australia

Stage 2 General Mathematics: discrete models, project scheduling and assignment. Activity-on-arrow conventions are used for project networks; technology may verify calculations but does not replace interpreting the model.

Official curriculum source ↗
Back to Networks, scheduling and assignment

Save your next step.

Create a free account to save your learning progress. Lessons and downloads stay free, with or without an account.

Create free account