Year 12 · Networks, scheduling and assignment · 20 min

Earliest/latest times

Turn event times into earliest and latest start/finish times for individual activities.

01 / LEARN

The idea, step by step

Four times for each activity

For an activity of duration d from event i to event j, its earliest start is the earliest time at i. Its earliest finish is ES+d. Its latest finish is the latest time at j, and its latest start is LF−d. An activity may have a range of allowed start times even though its duration is fixed.

The earliest head-event time is not automatically the activity's earliest finish: the head event may also wait for another, slower incoming activity. Keep the activity's own finish calculation separate from the merge time.

E⁢S=Ei,E⁢F=Ei+d,L⁢F=Lj,L⁢S=Lj−d
Forward and backward scans for the display network, with completion at day 13.
EventEarliest timeLatest time
100
244
338
488
51010
61313

Read a time window

Activity B in the display network has ES=0, EF=3, LF=8 and LS=5. It can therefore start anywhere from day 0 to day 5 without delaying the day-13 completion, provided the rest of the schedule follows the model. Activity C has ES=4 and EF=9, but the head event occurs earliest at 10 because E finishes later.

Use a precise interpretation: 'B may start at day 5 and finish at day 8' is clearer than 'B has five days spare somewhere'. These calculations assume durations are reliable and resources allow the listed parallel work.

A common trap

Taking an activity's earliest finish directly from the earliest time at its head event.

Instead: Calculate EF as the activity's own ES plus duration. The head event can occur later because of another incoming activity.

02 / WORKED EXAMPLES

See the thinking

Example 1

Use event values

An activity takes 6 hours. Its tail has earliest time 3 and its head has latest time 14. Find ES, EF, LS and LF.

  1. ES is 3.
  2. EF=3+6=9.
  3. LF is 14, so LS=14−6=8.
ES=3, EF=9, LS=8, LF=14 hours.
Example 2

Do not copy the head's earliest time

Activities P and Q finish at the same event. P starts at 2 and lasts 4 hours; Q starts at 5 and lasts 3 hours. Find P's earliest finish and the event's earliest time.

  1. P's earliest finish is 2+4=6.
  2. Q's earliest finish is 5+3=8.
  3. The shared event waits until 8.
P has EF=6 hours; the event occurs at 8 hours.

Check your understanding

An activity has ES=7, duration=4 and LF=13. What is its latest start?

Show answer

9.

It needs four time units before the latest finish, so LS=13−4=9.

03 / WORKSHEET

Your turn

6 questions · 15 marks · Work at your own pace.

Read the questions online
  1. Use the display project to find ES, EF, LS and LF for B.
    3 marks
    Forward and backward scans for the display network, with completion at day 13.
    EventEarliest timeLatest time
    100
    244
    338
    488
    51010
    61313
  2. Find all four activity times for C in the display project.
    3 marks
    Forward and backward scans for the display network, with completion at day 13.
    EventEarliest timeLatest time
    100
    244
    338
    488
    51010
    61313
  3. Find all four times for E in the display project.
    2 marks
    Forward and backward scans for the display network, with completion at day 13.
    EventEarliest timeLatest time
    100
    244
    338
    488
    51010
    61313
  4. A task lasts 8 minutes. Its ES is 12 and LS is 15. Find EF and LF.
    2 marks
  5. An activity runs 2→5 for 3 days. E2=6, E5=12 and L5=14. Find its earliest finish and explain why it differs from E5.
    3 marks
  6. A claimed schedule gives ES=5, EF=11, LS=9 and LF=14 for one fixed-duration activity. Identify the inconsistency.
    2 marks
Read the worked solutions

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. Use the display project to find ES, EF, LS and LF for B.
    3 marks
    Forward and backward scans for the display network, with completion at day 13.
    EventEarliest timeLatest time
    100
    244
    338
    488
    51010
    61313

    B is 1→3 of duration 3.

    ES=E1=0; EF=3; LF=L3=8; LS=8−3=5.

    0, 3, 5 and 8 days respectively.
  2. Find all four activity times for C in the display project.
    3 marks
    Forward and backward scans for the display network, with completion at day 13.
    EventEarliest timeLatest time
    100
    244
    338
    488
    51010
    61313

    C is 2→5 of duration 5.

    ES=4; EF=4+5=9; LF=10; LS=10−5=5.

    ES=4, EF=9, LS=5, LF=10 days.
  3. Find all four times for E in the display project.
    2 marks
    Forward and backward scans for the display network, with completion at day 13.
    EventEarliest timeLatest time
    100
    244
    338
    488
    51010
    61313

    E is 4→5 of duration 2.

    Use E4=8 and L5=10.

    ES=8, EF=10, LS=8, LF=10 days.
  4. A task lasts 8 minutes. Its ES is 12 and LS is 15. Find EF and LF.
    2 marks

    Add the same fixed duration to each start.

    12+8=20; 15+8=23.

    EF=20 and LF=23 minutes.
  5. An activity runs 2→5 for 3 days. E2=6, E5=12 and L5=14. Find its earliest finish and explain why it differs from E5.
    3 marks

    The task itself finishes at 6+3=9.

    An event combines all incoming requirements.

    EF=9 days; event 5 waits for another incoming activity until day 12.
  6. A claimed schedule gives ES=5, EF=11, LS=9 and LF=14 for one fixed-duration activity. Identify the inconsistency.
    2 marks

    11−5=6.

    14−9=5; the same activity cannot have both durations in this model.

    The duration would be 6 from ES/EF but 5 from LS/LF.
Checking saved progress…

Continue learning

Critical paths

Next lesson
Curriculum reference & lesson scope

SACE Board of South Australia

Stage 2 General Mathematics: discrete models, project scheduling and assignment. Activity-on-arrow conventions are used for project networks; technology may verify calculations but does not replace interpreting the model.

Official curriculum source ↗
Back to Networks, scheduling and assignment

Save your next step.

Create a free account to save your learning progress. Lessons and downloads stay free, with or without an account.