Year 12 · Networks, scheduling and assignment · 20 min

Slack and changes to activities

Calculate total float and assess delays or reductions without assuming every allowance can be used independently.

01 / LEARN

The idea, step by step

An activity's allowable delay

Total float is the difference between latest and earliest start: LS−ES. Equivalently, for an arrow from event i to event j with duration d, it is Lj−Ei−d. This is how far that activity may be delayed, with other relevant work scheduled consistently, before the chosen project finish is delayed.

In the display project, B has float 8−0−3=5 days and C has float 10−4−5=1 day. A, D, E and F have zero float. Float is not extra activity duration and does not mean a worker is occupied throughout the whole available window.

Total float=L⁢S−E⁢S=L⁢F−E⁢F=Lj−Ei−d

Change the network, then recompute

If B's duration rises from 3 to 7 days in the display project, E still waits until day 8 for D, so the overall finish remains 13. If B rises to 9 days, E starts at 9 and F finishes at 14. The old float correctly predicts when this branch begins to control.

After a change, recompute times rather than continuing to quote the old floats. Delays on connected non-critical activities may use the same path allowance; adding their separate original floats can overstate the delay that the project can tolerate.

A school display project. Times are in days.
ActivityDurationImmediate predecessors
A4None
B3None
C5A
D4A
E2B and D
F3C and E

A common trap

Adding the floats of successive tasks and treating the sum as extra spare time on that path.

Instead: Their total floats can represent the same scheduling allowance. Recalculate the full path or network for combined changes.

02 / WORKED EXAMPLES

See the thinking

Example 1

Compute float from a pair of events

A task lasts 5 hours, with tail earliest time 4 and head latest time 12. Find its total float.

  1. Use Lj−Ei−d.
  2. 12−4−5=3.
  3. This is the permitted delay before the selected project finish is affected.
3 hours.
Example 2

Two tasks share a branch allowance

A non-critical branch has two successive tasks P and Q. The branch takes 8 days while the critical route takes 11. Each task is reported to have 3 days total float. Can both be extended by 3 days without delaying the project?

  1. The branch has only 11−8=3 days of total route allowance.
  2. Extending both adds 6 days.
  3. The branch becomes 14 days and exceeds the old finish by 3.
No. Their allowances are shared along the branch; using both extensions delays completion to 14 days.

Check your understanding

A task has ES=3 and LS=8. It starts 4 days later than its earliest start. With no other changes, has it exceeded its total float?

Show answer

No.

Total float is 8−3=5 days. A four-day delay stays inside that allowance.

03 / WORKSHEET

Your turn

6 questions · 17 marks · Work at your own pace.

Read the questions online
  1. Calculate the total floats of B and C in the display project.
    3 marks
  2. Increase B's duration in the display project from 3 to 7 days. Find the project finish.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E
  3. Increase B's duration instead to 9 days. Find the finish and critical real-activity sequence.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E
  4. Activity P has ES=6, EF=10, LS=9 and LF=13. Find its duration and float.
    2 marks
  5. A non-critical route takes 12 hours and the project finishes in 16. Two consecutive tasks on that route are both extended by 3 hours. What happens?
    3 marks
  6. The project deadline is fixed at day 20, but its earliest completion is day 18. Explain why a backward scan using 20 answers a different question from one using 18.
    3 marks
Read the worked solutions

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. Calculate the total floats of B and C in the display project.
    3 marks

    B: 8−0−3=5.

    C: 10−4−5=1.

    B: 5 days; C: 1 day.
  2. Increase B's duration in the display project from 3 to 7 days. Find the project finish.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E

    E waits for max(B finish 7, D finish 8)=8.

    E finishes 10 and F finishes 13.

    13 days.
  3. Increase B's duration instead to 9 days. Find the finish and critical real-activity sequence.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E

    E starts at max(9,8)=9.

    It finishes 11; F finishes 14.

    The B branch now controls.

    14 days; B–E–F.
  4. Activity P has ES=6, EF=10, LS=9 and LF=13. Find its duration and float.
    2 marks

    Duration=10−6=4 (also 13−9=4).

    Float=9−6=3.

    Duration 4; float 3 time units.
  5. A non-critical route takes 12 hours and the project finishes in 16. Two consecutive tasks on that route are both extended by 3 hours. What happens?
    3 marks

    Its shared allowance was 16−12=4.

    The combined extension is 6, so it exceeds the allowance by 2.

    That route becomes 18 hours, delaying the project by 2 hours.
  6. The project deadline is fixed at day 20, but its earliest completion is day 18. Explain why a backward scan using 20 answers a different question from one using 18.
    3 marks

    A looser finish target creates two days of overall schedule allowance.

    State the finish target before interpreting zero or positive float.

    The day-20 scan finds latest times that meet the deadline; the day-18 scan finds float that preserves the earliest completion.
Checking saved progress…

Continue learning

Assignment cost tables

Next lesson
Curriculum reference & lesson scope

SACE Board of South Australia

Stage 2 General Mathematics: discrete models, project scheduling and assignment. Activity-on-arrow conventions are used for project networks; technology may verify calculations but does not replace interpreting the model.

Official curriculum source ↗